Northwestern University Lab Renovation

May 26, 2006

Demolition continues

Filed under: Uncategorized — owenpriest @ 3:11 pm

The demolition continues. Notice the wall dividing the two labs has been completely removed.

May 24, 2006

Hole for new door

Filed under: Uncategorized — owenpriest @ 3:06 pm


A hole for the new door in the back of the lab has been made and boarded up.

May 23, 2006

Proctective barriers for new doors installed

Filed under: Uncategorized — owenpriest @ 3:04 pm

A proctective barrier has been installed in the back hall where a hole  will be knocked in the wall for a new door.  This barrier will help cut down on dust and noise while the hole is made and the new door is installed.

May 19, 2006

Noisy/Heavy demolition on 2nd floor should be complete, Tuesday (5/23).

Filed under: Announcements — owenpriest @ 2:47 pm

Heavy construction during week of 5/22 will include breaking through north wall of lab. Plywood partitions will be installed for noise/ dust protection. Most work will be done early in morning before students/faculty arrive.

Old vs. Demolished Part of Lab

Filed under: Pictures — owenpriest @ 1:17 pm


These two pictures are taken from roughly the same perspective in the labs. The picture on the right was taken last fall and the one on the left was taken after removal of the wall dividing the two labs.

Wall Removed

Filed under: Pictures — owenpriest @ 11:43 am


The central wall separating the old labs has been mostly removed.

May 18, 2006

HVAC switchover pushed back

Filed under: Uncategorized — owenpriest @ 10:58 am

 

Due to the delayed delivery of chilled water valves we need to push the switch over shut-down for the new air handler back to 7:00 AM 3 June through 7:00 AM 5 June. This shut-down was originally scheduled for the 20-21 May weekend. We will keep minimal exhaust air flowing in the wing during the shut-down.

May 16, 2006

Demo Machine

Filed under: Uncategorized — owenpriest @ 11:38 am


The demo machine arriving on site. It will be used for the heavy demolition in the labs.

Demo Machine

Filed under: Uncategorized — owenpriest @ 11:37 am


Demo machine arriving by elevator.

May 12, 2006

D-wing Demolition Delay

Filed under: Uncategorized — owenpriest @ 4:36 pm

Demolition on the Tech second floor D wing will start on Monday, May 15, and is expected to be complete by Friday, May 19.